Fast-track minimum-flow powerhouse & siphon solution at Swinging Bridge Hydroelectric Project

Eagle Creek Renewable Energy (ECRE) required engineering design services to design a new minimum flow powerhouse at the Swinging Bridge Project. The purpose of this project was to add a new powerhouse, adjacent to the existing Unit #2 powerhouse and minimum flow release valve, with a minimum flow unit (Unit #3) capable of generating within the existing 60 to 100 cfs minimum flow requirement during periods when Unit #2 is not in operation. Before 2017, ECRE had entered an economic incentive contract with the New York State Energy Research and Development Authority (NYSERDA) requiring the project to be commercially operational by December 31, 2019.

Kleinschmidt worked closely with ECRE as we coordinated the civil/structural design to incorporate Mavel’s water-to-wire equipment package, and Eaton Electric’s design, supply, and installation of the high voltage and balance of plant electrical and water-to-wire controls package to develop a conceptual layout for the new powerhouse for Unit #3. Access during construction, long-term operation, eliminating/reducing rock removal to reduce project costs were primary considerations. We considered the orientation of the tailrace for constructability, long-term operation, tailrace turbulence/headloss, and impacts to the berm protecting the upstream high-hazard earthen dam. Mid-project, ECRE and the New York Department of Environmental Conservation (NYDEC) noted language within the FERC license that requires the minimum flow to be provided at all times. Kleinschmidt’s proposed solution was for a minimum flow siphon system capable of delivering a minimum of 60-cfs when the Unit #2 penstock was dewatered. The siphon system is a 28-inch interior diameter HDPE pipe that allows ECRE to throttle the outlet manually. Kleinschmidt’s final design included drawings and specifications with sufficient detail for a qualified contractor to bid, procure materials, and construct the project. We assisted ECRE throughout construction by reviewing submittals, answering RFIs, and providing office assistance to answer miscellaneous questions from the field. We also performed periodic visits to the project site to observe construction activities.

Kleinschmidt coordinated closely with Mavel and Eaton Electric to assist ECRE in expediting the project schedule and coordinated the design elements from all three into a single design package for the Contractor. Kleinschmidt helped ECRE achieve economic incentives by providing an Independent Engineer’s (IE) report certifying that the project was commercially operational by December 31, 2019, to support ECRE’s NYSERDA application. This schedule was met even with the addition of the siphon system to the overall design and construction schedule.

Client:

Eagle Creek Renewable Energy

Project Location:

Sullivan County, NY

Services Provided:

  • Minimum Flow Powerhouse Design
  • Minimum Flow Siphon Design
  • Regulatory Strategic Planning
  • Bid Specifications & Drawings
  • Construction Services

Project Timeframe:

2017-2020

A Trusted Partner:

Since 2011

Regional Vice President

Kevin Cooley, P.E.

Kevin Cooley specializes in the evaluation, planning, design, and rehabilitation of hydroelectric projects.  He has been with Kleinschmidt for over 24 years and is currently Regional Vice President of the Northeast US and Canada, formerly serving as Director of Kleinschmidt’s Engineering Division.  As Regional Vice President, Kevin is responsible for Kleinschmidt’s project execution in the...

Let's
Chat!

This field is for validation purposes and should be left unchanged.